After a large-scale reconstruction, the “Yubileynaya” power substation, located in the historical part of Odesa, has started operating at full capacity.
New switchgear for “Yubileynaya” was designed specifically for the existing substation building. It was important to place the equipment on two floors simultaneously, rather than the standard one. This solution allowed for not expanding the substation’s territory in the historical area.
The substation’s reconstruction has increased the voltage class from 35 to 110 kV, making the city center’s power supply more reliable. Therefore, energy workers say, power outages in the city center will become a rare occurrence.
According to the General Director of JSC “Odesaoblenergo” Oleksandr Fomenko, the substation reconstruction cost the company 77 million UAH. He also mentioned that the company has developed a five-year development program, which includes the complete reconstruction of three substations in Odesa and the construction of two more. This will help meet the city’s and region’s needs for high-quality power supply.