Only by joining forces can the shareholders, the city authorities, and the company “Olimpex Trans” complete the construction of the multi-story residential complex at 3/1 Zhabotinsky Street.

The history of modern Odesa is also a history of unfinished buildings. Every high-rise building abandoned by the developer has its own “tragic story.”

The multi-section residential complex at 3/1 Zhabotinsky Street also has one. It’s located at the 6th Station of Bolshoy Fontan. The construction of the high-rise was carried out by the infamous “Naberezhny Kvartal” group. This developer “gained notoriety” for carrying out work on all its sites in Odesa with gross violations of construction norms and regulations. And after the “NK” group was finally asked on what grounds it allowed itself such liberties, it simply disappeared. Naturally, along with the money of citizens who acted as shareholders (co-investors) of the new building.

Construction of the residential complex at 3/1 Zhabotinsky Street ceased over a year ago. This was preceded by an inspection by the State Architectural and Construction Inspectorate of Ukraine in February 2016. As a result, the supervisory body revoked the developer’s construction permit on the grounds that “Naberezhny Kvartal” had illegally expanded the construction area, and the building itself became five stories higher than provided for in the project. At the same time, the sale of square meters not indicated in official documents was actively carried out.

The developer responded “originally” to the claims of the State Architectural and Construction Inspectorate. They took off. In early October last year, a lock appeared on the office of the servicing cooperative “Naberezhny Kvartal – Zhabotinsky,” which sold housing on Zhabotinsky Street, and the phones went silent. Lawsuits began, and criminal proceedings were initiated against officials of the “Naberezhny Kvartal” group.

The eternal questions arose in such cases: “Who suffered?”, “Who is to blame for what happened?”, and “What should be done?”.

The first two are not difficult to answer. First and foremost, people suffered – the co-investors of the construction, most of whom paid 100 percent of the cost of their share (apartments, storage rooms, parking spaces, office premises). The company “Olimpex Trans,” the land lessee and the client for construction, also received the status of a victim within the criminal proceedings, as “Olimpex Trans,” like ordinary shareholders, did not receive the square meters due to it. Odesa as a whole also undoubtedly suffered, which the fraudulent developer “rewarded” with another unfinished building.

Who is to blame for the fact that the facility at 3/1 Zhabotinsky Street is still frozen? It is clear that at the forefront of this dubious rating is the “Naberezhny Kvartal” group. We really want the criminal proceedings against its officials to be brought to a logical conclusion – to a fair court verdict on the facts of fraud and punishment of the guilty.

However, the shareholders themselves bear some responsibility for the fact that construction has stopped. They should have reacted more actively when the first alarming signs appeared. Alas, to hide the truth, in our society, people have become so accustomed to the widespread disregard for the law that the absence of certain necessary permits for the developer did not bother the shareholders. The client for construction also bears some responsibility for what happened. If “Olimpex Trans” had more “strictly” controlled the work of “Naberezhny Kvartal” on Zhabotinsky Street, the current situation would certainly not have happened. Well, and the city authorities, in the person of certain officials, are undoubtedly to blame. After all, the first signals of deviations from the approved project appeared not at the end of 2015, but much earlier. If the authorities had reacted properly then, people would not have suffered.

However, all this is in the past. Today, we need to think about how to rectify the situation, in particular, what needs to be done so that citizens who invested in the construction of the residential complex do not lose their money.

And here, as they say, there are options. We would very much not like the development of the situation around the construction on Zhabotinsky Street to go down a dead-end path, which is characterized by dragging out the process. This is when everyone waits for the end of endless lawsuits and criminal proceedings, only to make a decision afterward. But this could take – as practice shows from attempts to “resuscitate” other long-term construction projects – a good ten years. It is clear that such delays will only benefit someone, as it will help avoid deserved punishment for certain offenses committed during the construction of the residential complex.

But there is no point for the victims of the construction fraud to wait! Especially since there is an option for resolving the situation that will allow people to receive the housing they paid for. Its essence is as follows:

1. The client for construction modifies the original project to bring it into line with reality, because, we repeat, almost all premises in the building have been sold.
2. The city authorities, considering the exceptional nature of the situation, approve the entire package of documentation necessary to resume construction. They punish officials who have been turning a blind eye to the violations of “Naberezhny Kvartal” for a whole year.
3. Shareholders who signed an agreement with the “Naberezhny Kvartal” group agree to a minor additional financing.
4. The state, in the person of investigators, prosecutors, and judges, helps to return the stolen money to the affected investors.

The implementation of this plan depends on the synchronization and coordination of actions of those who are interested in resolving the problem. But the first – and very important! – step must be taken by the city authorities, in the person of the Mayor of Odesa Gennady Trukhanov, his deputy Petro Ryabokon, and the head of the capital construction department Boris Panov. We believe that they will heed the above proposal of the shareholders. This will allow people to receive their long-paid-for apartments in the near future, rather than in ten to fifteen years.