According to the publication “Ports of Ukraine”, the Antimonopoly Committee of Ukraine (AMCU) has accepted for consideration the complaint of the company DP “Van Oord Ukraine”, which believes that the Yuzhny branch of the State Enterprise “Administration of Sea Ports of Ukraine” (SE “AMPU”) violated the law during the procurement of dredging services. The hearing of the complaint is scheduled for February 8.
We remind you that “Vechernaya Odessa” in the article “Will we deepen the bottom or corruption?” (issue of December 22, 2016) described in detail how the tender was conducted and why the company DP “Van Oord Ukraine” felt offended. The results of the tender caused a scandal. The results of the tender were commented on by Prime Minister V. Groysman himself, who, in fact, demanded a repeat of the event. The Antimonopoly Committee complied with the head of government’s instruction to cancel the results.
In the second half of November, the Yuzhny branch of SE “AMPU” announced a new tender for the project “Reconstruction of the sea approach channel and internal water approaches to the deep-water berths of the port of Yuzhny”. After the completion of work on the internal and approach channels of the port, depths of 21 meters will be reached, and in the operational water area of berths No. 5, 6 of SE “MTP “Yuzhny” – 19 meters.
The adjusted project of the facility was approved by the order of the Cabinet of Ministers No. 674-r of September 14, 2016. During the work, it is planned to remove 3.4 million cubic meters of soil. The expected cost of the work is about 1 billion UAH.
Tender procurements have also been announced for the construction of the first commissioning complex of the first stage of the facility “Reconstruction of water approaches, maneuvering zones and operational water areas at berths, taking into account the prospective cargo turnover of the port of Yuzhny”. After the completion of the work, it is expected to reach depths of 16 meters on the water approaches and in the water areas of berths No. 23-25. Dredging is being implemented within the framework of the agreement on the creation of a new grain terminal between the Administration of Sea Ports of Ukraine (AMPU) and the company “M. V. Cargo”, signed in March 2016. The feasibility study of the project was approved by the order of the Cabinet of Ministers No. 657-r of September 8, 2016. During the work, it is planned to remove 4.4 million cubic meters of soil. The expected cost of the work is 1.435 billion UAH.
Finally, the “Administration of Sea Ports of Ukraine” announced a tender for operational dredging in the internal water area of the port and the internal approach channel. During the work, it is planned to remove 550 thousand cubic meters of soil. The expected cost of the work is 158 million UAH.