Work continues on completing houses abandoned by the “Alliance” corporation at various stages of construction. Thanks to the efforts of the city authorities, a 200-apartment residential building on Vysotskogo Street was commissioned in March of this year. The construction of four more “Alliance” houses is nearing completion, meaning more than 470 Odesa families will celebrate their housewarming in September.
Currently, work on these sites is in its final stages. On Marselska Street, where two 16-story buildings are located (construction № 1 and № 1a), all major works, including landscaping, have already been completed. Finishing of common areas is underway. It is planned that this work will be completed by the end of summer.
Another 16-story building is under construction on Vysotskogo Street (construction № 27). Facade finishing is currently being completed there, and connection to utility networks is in progress. Next, landscaping of the adjacent territory will be carried out. Investors of the unfinished buildings are ready to take an active part in the cleanup and have already set a date for a community work day.
On Lyustdorfskaya Road (construction № 36), a 16-story residential building has also been erected. On-site, interior painting, facade work, common area outfitting, and glazing have been fully completed. Connection to utility networks and landscaping will begin in the near future.