Reconstruction of the Southern Drainage Basin Sewerage System Has Begun in Odesa.
The collector serving the southern part of the city was built in the 1980s. The pressure pipeline is made of steel pipes, whose service life of 25 years has already expired. Non-compliance with technological requirements also affected the reduction of its service life.
According to the press service of the city council, the development and selection of a new drainage system scheme was carried out by an international consulting company based on a comparative analysis of 10 drainage schemes, taking into account many technical and financial-economic aspects. A scheme has been selected and agreed upon with the International Bank for Reconstruction and Development, the essence of which is as follows. The transportation of domestic and part of storm sewage will be carried out from the Arcadia district through a tunnel 1670 m long, built during the Soviet era.
It is also planned to construct a deep-lying pumping station (KNS-7A) (depth of about 30 m), which will direct sewage through a pressure collector (Vanny Lane, Fontanskaya Road, Kostandi Street, Raventstva Street) to KNS-6A, from where it will be gravity-fed to the main pumping station (KNS-6B) through an existing deep-lying collector. Further, the sewage will be directed to the treatment facilities through two existing pressure pipelines.
The implementation of the reconstruction project for the main part of the Southern Drainage Basin Sewerage System of Odesa is planned within the framework of the joint project with the International Bank for Reconstruction and Development “Urban Infrastructure Development” using funds from the Loan Agreement between Ukraine and the IBRD, adopted in 2008.
The customer for the design and execution of the works, in accordance with the decision of the Odesa City Executive Committee, is the Municipal Enterprise “Odesa Development Programs Agency”. According to its head, O. Dudnik, the reconstruction of the sewerage system in the southern part of Odesa is a strategically important task for the city’s development, as the existing system is currently in an emergency state. The reconstruction will reduce the number of accidents and prevent untreated sewage and storm runoff from entering the sea, as well as pollution of the coastal strip, including beaches.
All work is planned to be completed by the end of 2013.
The city authorities assure that during the reconstruction of the main part of the sewerage network, inconvenience for Odesa residents will be minimized. A phased work schedule will allow for not completely blocking traffic. Thus, the press service of the deputy mayor S. Podgainy reported that when builders are working on Fontanskaya Road, the carriageway may be narrowed to two lanes (instead of four). Other streets affected by the reconstruction will also be partially closed. The movement of special transport and vehicles owned by residents of the territory will be ensured. Traffic schemes will be published on the official city website.
In addition, the mayor’s office reports that the damaged road surface during the work will be restored by the company “Akvaspetsstroy,” which is involved in the reconstruction of the main line. And on Raventstva Street, which is unpaved, asphalt will be laid.