The house on the corner of Ekaterininskaya and Malaya Arnautskaya streets has been under scaffolding for almost three years. A sign on the fence announces that repair work is underway to restore the facades and roofs of buildings in the historic part of the city. The customer is the Capital Construction Department of the City Executive Committee, and the contractor is LLC “Odessa Restoration Workshops”. There is not a single person on the scaffolding.
This house, along with 52 other buildings, found itself at the center of the so-called “facade scandal.” The previous city administration planned to restore the facades and roofs of buildings in the city center. Work began on two dozen sites simultaneously, but in October 2010, after a change in city leadership, it was suspended. The contracting firm was accused of performing work that did not comply with technology and was carried out without permits. Furthermore, according to the current mayor A. Kostusev, the contractor was chosen illegally for the restoration, without a tender. Last year, work resumed, and in December 2011, restoration was completed on several sites. The house in question was not among the “lucky ones.”
“The residents of our house are eagerly awaiting the completion of the repairs,” wrote the residents of house No. 60 on Malaya Arnautskaya Street to the editorial office of “Evening Odessa.” “We still don’t understand why it was necessary to remove the plaster from the facade of the house in late autumn, on the eve of winter, exposing the walls of shell rock. Couldn’t it have been foreseen that the facade of the house could not be restored in a short period? There was too much work to be done: the length of the building along Malaya Arnautskaya Street is 50 meters, and along Ekaterininskaya Street, it is over 200 meters. We hoped that the builders understood that the work could not be delayed, and bare shell rock would not withstand the harsh weather.”
…The communal apartment on the third floor, where six families live, is kept tidy by the residents. However, peeling plaster on the ceilings, crumbling tiles in the bathroom, and mold stains on the walls and under the windows spoil the impression. Since the builders stripped the outer plaster, removed the sills and window ledges, any rain becomes a natural disaster.
Valentina Grigoryevna Eseva pushes aside the curtain from the window. The wall from the windowsill to the floor is covered in stains, and the corner under the ceiling is streaked – these are the traces of recent rain. Rainwater also penetrates into the room of Evgenia Andreevna Kolesnikova through the cracks in the windowsill.
“Can it be any other way?” says Nikolai Fedorovich Koval. “Shell rock not protected by plaster absorbs moisture, and besides, water gets into the apartments during rain between the joints of the slabs. And here is the result: dampness and mold in the apartments.”
In addition to the plaster, the builders also removed the roof, covering the hole with a plastic film, which the wind repeatedly blew away. After the residents complained to the capital construction department and a visit from the head of the Capital Construction Department, the house was covered with slate. However, above V. G. Eseva’s apartment, the roof still leaks, and during the last downpour, the ceiling in her room was significantly damaged.
People are trying to fix the consequences of the leaks on their own, but their rooms already need repairs, which makes no sense to carry out before the restoration is completed.
In March of this year, at an extraordinary session of the city council, the “People’s Budget” program was adopted, according to which 24.4 million UAH were allocated for the repair of facades in the historic part of the city. Last week, the executive committee approved a list of facades (house No. 60 on Malaya Arnautskaya Street was included in this list) whose reconstruction should be carried out at the expense of subsidies from the state budget. The city expects to receive 19.5 million UAH for these purposes. At the same time, the estimated cost of restoring 52 buildings is 157 million UAH. Work will begin after a tender is held to select a contractor who will replace the firm “Odessa Restoration Workshops.”
Will the residents of the house live to see the end of the repairs, at least before the rainy season?