As “Vechernaya Odessa” has already written (issue 60 of April 24, 2012: “Will Marazlievskaya” come before the end of the world?”), the construction of the substation building is to begin in September of this year. Chairman of the Board of OJSC “Odessaoblenergo” Alexander Niverchuk confirms: we are starting on time. Together with Odessa energy workers, the Ministry of Fuel and Energy, the regional administration, and the city authorities are making every effort to achieve this.
Now, so much is being written in the press about the “Marazlievskaya” substation that it seems there is no one who doesn’t know about this project. Such attention is understandable. After all, with the appearance of a new substation, the power supply in the center of Odessa will cease to be a common topic of conversation.
But will Odessa energy workers have enough financial gunpowder? After all, no matter what project we talk about, the conversation invariably turns to money. And here, it seems, considerable investments are required. Where will they come from?
— The investment program is formed by us, mainly, at the expense of depreciation charges, profits that shareholders invest in the development of our company’s networks, — explains Alexander Nikolaevich. — As well as from other income in the form of sales of reactive power. At one time, in the 90s, there was a very difficult situation in the energy sector with network development. And then those who came from the old system called such investments investments. But, in essence, we are talking about a network development program using our own resources. As for the “Marazlievskaya” substation, our company will build it as the owner. We want to bring the power supply of the center of Odessa, and not only it, to a higher level.
According to the chairman of the board, the first stage of renewal, which consisted mainly of so-called “patching holes,” is coming to an end. Energy workers have closed most of the “holes.” Now, in the very complex electrical economy of our region, it is the turn of the high-voltage part and cable lines with a voltage of 6-10 kV. To a lesser extent, the renewal concerns low-voltage networks, which are considered internal to buildings. Here, the ownership of these networks by other parties interferes, and energy workers have not yet reached the stage of “managing” these networks.
The complexity of the changes being carried out by the power supply company lies in the fact that they are carried out under voltage. In several senses of the word. This includes the internal tension of people, on whose shoulders a considerable burden has fallen. And the voltage in the networks. Energy workers do not want, and by law are not entitled, to disconnect domestic consumers for more than a day. Therefore, their tactics are understandable: using switching, they temporarily take equipment out of operation, put it in order, and if necessary, replace it. Then, having switched consumers back to another line, they return the equipment to the previous scheme. And so, stage by stage.

It should be noted that if the usual construction period for a substation is about a year and a half, then the reconstruction of existing equipment takes much longer. In other words, renewal takes three and a half to four years. This was the case in Arcadia and in the Kotovsky residential area, it is now in the Tairovsky residential area, and will be in Artillery and in the South-Western district.
But this approach is impossible in the center of Odessa, because it (the historical center) is inside a geometric figure outlined by lines passing through the “Chumka” and “Yubileynaya” substations and the TPP. And there is no way to carry out switching here.
The “Marazlievskaya” substation, on the other hand, is a completely new approach. It goes directly to the center, with complete autonomy. In other words, separate from the existing networks, which have been “alive” for the second century. With the connection of consumers to the new network, it becomes possible to reconstruct the old one.
At the same time, energy workers are creating a significant reserve for the future. According to their estimates, after it comes into operation, the “Marazlievskaya” substation will solve the constant headache associated with the quality of electricity supply for the next fifteen to twenty years. At the same time, it will provide an opportunity to open up a front of work for the same time period.
But let’s return to one of the most important components of the project — financing. In the National Commission for Regulation in the Energy Sector (NCRE), “Odessaoblenergo” has proven with its clear calculations that the overwhelming share of investments will be profit along with other own funds. Of course, the decision on such an investment was previously made by the shareholders. In addition, the NCRE is raising the issue of part of the construction being financed through connection fees. This refers to new consumers who wish to receive electricity from “Marazlievskaya.” Thus, they will also contribute their share to this project. At the same time, it will not be so much of the required capital investments, but still.
Well, the total cost of the project will be from 370 to 520 million hryvnias. A specific figure can be determined when the “land issue” is finally resolved.
Interestingly, the laying of new networks will cost more than the substation itself. And to supply this network, the reconstruction of another network, the one that supplies it with high-voltage energy, is beginning. Now, with the completion of the tender, “Odessaoblenergo” is starting the renewal of the 110 kV line, which is located in the alignment of the “Usatovo” and “Tsentrolit” high-voltage substations.