On Friday, a press conference titled “Participation of a German Investor in Financing the Deep-Water Terminal Construction Project ‘Quarantine Mole’ at the Port of Odessa” was held at the administration building of the Odessa Sea Commercial Port. Journalists’ questions were answered by the Extraordinary and Plenipotentiary Ambassador of Germany to Ukraine, Mr. Hans-Jürgen Geimzöth, Managing Director of “HPC Hamburg,” President of SE “HPC-Ukraine,” Mr. Klaus Schmöcker, Head of the Kyiv Office of the International Finance Corporation (IFC), Mr. Rufat Alimardanov, Mr. Rolf Grunwald, representing the German Investment and Development Company DEG, and Mykola Panteleimonovych Pavliuk.
The news that the International Finance Corporation, which provided a $32 million loan, and the German company DEG, which allocated $14 million on a long-term basis, acted as financial partners for the first stage of the “Container Mole” terminal construction, which is being jointly built by SE “Odessa Sea Commercial Port” and the German subsidiary “HPC-Ukraine” (Vechernaya Odessa wrote in detail about this project in its issues of June 21 and 25 of this year), served as the occasion for the press conference.
— For our organization, participation in the container terminal construction project will be the first experience in the transport industry, — noted the head of the IFC’s Kyiv office, Rufat Alimardanov. — We believe that this investment program will be a serious step towards modernizing Ukraine’s port economy. The example of the Port of Odessa should be exemplary for other container terminal operators who also want to increase the capacity of their production facilities. Ultimately, this will lead to a significant inflow of private investment into Ukraine’s transport infrastructure.
We remind you that the construction of the “Container Mole” terminal began in April last year. At that time, in the presence of the regional governor Eduard Matviychuk and the Extraordinary and Plenipotentiary Ambassador of Germany to Ukraine Hans-Jürgen Geimzöth, the first pile was ceremonially driven. To date, the port has completed the excavation work for the berths. 22,000 tons of metal pipes for pile manufacturing have been delivered, and 1272 out of the required 1302 piles are ready. The port has spent slightly over 800 million hryvnias on the project’s implementation.
The first stage of the “Quarantine Mole” facility construction also includes coastal reinforcement work, filling the berth with sand, and connecting the constructed container terminal area with the existing one, where SE “HPC-Ukraine” acts as the operator. All these works are to be carried out by the German company “Moebius Bau AG,” which won the tender.
The second stage of the project implementation involves the creation of a warehouse area of 19.3 hectares. Well, then the container complex will need to be equipped with appropriate port machinery.
The complete construction of the terminal is expected to be finished in 2014, with the first stage of work ending in May 2012. As for the first vessels, the new container terminal, according to the president of SE “HPC-Ukraine,” Klaus Schmöcker, will be able to receive them in 2013.
The only thing that concerns the German partners — and seriously! — is the economic and political instability in Ukraine. According to K. Schmöcker, they closely followed the events in the Odessa Sea Commercial Port over the summer, constantly consulting with their embassy, trying to understand how the criminal prosecution of N. Pavliuk would affect previously concluded agreements. Unfortunately, as Hans-Jürgen Geimzöth noted, in Ukraine, after last year’s local elections, an unfavorable trend has emerged: new officials and “servants of the people” easily abandon contracts concluded by their predecessors from the previous government.
However, as the president of SE “HPC-Ukraine” admitted, foreign investors have not directly experienced any problems in connection with the criminal cases initiated against the head of the Port of Odessa. No one bothered them, no one summoned them. Well, the fact that Mykola Panteleimonovych has returned to his workplace inspires optimism and confidence among the German partners that the construction of the “Container Mole” terminal will proceed strictly according to schedule.
True, the fact that N. Pavliuk, appearing before the press for the first time after the summer events, was already acting as the Honorary President of SE “Odessa Sea Commercial Port” remained somewhat behind the scenes. In fact, this post is equivalent to an advisor position. Under the new head of the port. Who that will be is still unclear.
Based on this, it can be assumed that the economic and diplomatic efforts of the German investors have to some extent helped Mykola Panteleimonovych remain in the management of the state enterprise. His assistance will be needed to ensure that the terminal is built on time. After all, problems in Ukrainian realities usually appear where you least expect them.
For instance, when SE “HPC-Ukraine” conducted the tender for participation in the first stage of construction, one of the main conditions was that the company had a license for sand extraction. Two participants, including “Moebius Bau AG,” reported that they had such a permit. Thus, there were two contenders left for the tender. In the end, “Moebius Bau AG” won. But soon, the German company’s sand extraction license was revoked, with the explanation that a new one was needed.
This unforeseen circumstance pushed the start of sand extraction work back to November 10. By this date, “Moebius Bau AG” expects to obtain the license. To not lose a single moment, the Germans have already brought dredging equipment to the port’s waters, which is ready to start work at any moment.