Seven new schools will open in the Odesa region by September 1. One of them is in the village of Pavlovka, Frunzivsky district. This was planned by the regional leadership and the deputy corps when the decision was made to allocate 7.5 million from the regional budget this year to complete this facility. Will the builders manage to complete it within the deadlines stipulated by the contracts? This question was asked by the Chairman of the Odesa Regional Council, Mykola Pundyk, who paid a working visit to the Frunzivsky district.
Until recently, Pavlovka schoolchildren studied in an old, adapted building constructed in 1904. The new two-story school is designed for 200 students and will meet modern standards for educational institutions of this type.
— The project complies with the state standards that existed when it was created. Of course, it is probably partially outdated by today’s standards. For example, I expressed my remarks to the contractor, particularly regarding the bathrooms, and I will discuss this with the management of UKS. I think we will make some changes. But, overall, it is a modern school, — believes Mykola Pundyk.
The total cost of the facility is over 11.1 million hryvnias. In 2006-2010, work worth over 3.5 million hryvnias was financed from the state and regional development budgets. The remaining funds were allocated this year for the completion of work, the purchase of furniture and equipment for the school. A lot has been done: the building has been erected and plastered (both externally and internally); the roof has been covered, metal-plastic windows and doors have been installed. External and internal water supply and sewage networks have been connected, fire reservoirs have been installed, a boiler room has been built, and landscaping has begun.
However, the volume of remaining work caused fair concerns for the chairman of the regional council: will it be possible to complete the construction and fully equip the school on time? The contracting firm (PE “Multigroup”) promises to mobilize its forces, increase the number of workers, and complete the facility on time.
— The contractors promise that the first bell ceremony will take place in the new school. This is very important, as the village has good prospects. The birth rate has increased, and there are not enough places even in the kindergarten. We are glad that there are such excellent indicators in the northern part of the region. And we will do everything to support these trends, — says the head of the regional council.
After talking with the village head, Mykola Volodymyrovych noted another issue that the regional council can help the people of Pavlovka with.
— There are many problems here. The biggest one is, of course, the roads. But this is not only a problem for the Odesa region, and we can do little here. But what we can really do is help solve the water supply problem. I think at the next session, we will make one amendment to the budget schedule and allocate funds for another water tower to be built in this village, — promised Mykola Pundyk and immediately added: — Of course, this problem is relevant for our entire region, and it needs to be solved.