A terminal is born amidst the waves

Last Friday, the head of SE “Odesa Sea Commercial Port” Mykola Pavliuk and the General Director of “GPK-Ukraine” – a subsidiary of the German company “Hamburg Port Consulting” – Dirk Butterman, solemnly signed a memorandum on the ratification of the agreement on investing funds in the construction of a container terminal on the Quarantine Mole and an agreement on joint financing of design work for the construction of the aforementioned facility.

In accordance with these documents, the total cost of the project is almost 4.5 billion hryvnias. Construction will take 36 months. As reported, on April 10 of this year, the first pile was driven into the foundation of the future container terminal, which will be an extension of the existing terminal on the Quarantine Mole.

The investments required for construction will be shared equally by SE “OSCP” and “GPK-Ukraine”. The port will build the berth line, a 900-meter breakwater, and carry out dredging work in the water area, achieving a depth of 15 meters, at its own expense. The German side will build the shore protection structures that will connect the new berth to the existing territory, as well as create a storage area by reclamation, widen the road leading to the transport overpass, and equip the terminal with transshipment equipment.

Dirk Butterman (left) and Mykola Pavliuk discuss the progress of terminal construction
Dirk Butterman (left) and Mykola Pavliuk discuss the progress of terminal construction

— In August, the contracting organization – the firm “Mastbud” – began driving piles, — noted the head of Odesa Sea Commercial Port, Mykola Pavliuk. — A total of 1302 piles are to be driven. Despite the fact that, according to the project, construction work is planned for three years, the firm “Mastbud” promises to build the terminal within two years. By the end of this year, it is planned to drive all the piles for the 300-meter berth, and the port’s partner – “GPK-Ukraine” – must fill its “body” with sand. As a result, by the end of the year, the berth will be ready and the sand will be reclaimed. In addition, the German side will begin the construction of the southern and northern shore protection structures, and build the road leading to the 4th stage of the overpass. The port will build another 350 meters of berth and a breakwater next year, and our partners will arrange the storage area.

The capacity of the reconstructed container terminal on the Quarantine Mole will be 1 million 200 thousand TEU.