Usatovo, Nerubayka: High Voltage
For six months, the construction of the high-voltage power transmission line “Adzhalik — Usatovo” has been underway, and all this time, local residents of two villages in the Belyaevsky district — Usatovo and Nerubayka — have not stopped fighting. They demand that the line be moved beyond the borders of the settlements.
Many of them know well what it’s like to live under a power line: for 47 years, the wires of the “MoldGRES — Usatovo” power line hung over their gardens, near their homes. People are convinced that they acquired many illnesses as a result of the increased electric field. They can’t go out into the garden to work: every metal object gives an electric shock. They hoped that when the decision was made to build the new “Adzhalik — Usatovo” power line outside the settlements, the single-circuit “MoldGRES — Usatovo” line would also be rerouted there. But the energy company abandoned the original plan: they are reconstructing “MoldGRES” along the old route and building “Adzhalik — Usatovo.”
The European Bank for Reconstruction and Development, which is financing the construction of the new facility, as well as the regional leadership, was forced to react to the strong protests of local residents. For a time, the work was suspended by order of the governor, and the EBRD threatened to suspend funding for the power line until the conflict with the population was resolved.
Today, everything has returned to its former state: work is in full swing, and no one is particularly reacting to people’s outrage. It seems that meetings between energy company representatives and local residents are being organized “for the sake of appearance” to, so to speak, relieve social tension.
Such a meeting took place in Nerubayka on February 17. Anatoly Shvedky, First Deputy Director of the Southern Power System of the National Energy Company “Ukrenergo,” Petr Moiseev, Deputy Director of the Southern Power System, Konstantin Yavorsky, Deputy Director of “Ukrenergo,” Natalia Makarenko, Chief Project Engineer, and others arrived. As the organizers of the meeting reported, their visit to Nerubayka was related to the EBRD’s request for additional public information. In fact, those present could hardly expect any new information, Anatoly Shvedky warned, everyone is already well aware of the ongoing work.
The “Adzhalik — Usatovo” line was designed and approved by Resolution of the Cabinet of Ministers No. 327-r of August 9, 2005, Petr Moiseev reported. When they started implementing this project, they encountered a number of difficulties. According to the original project, the line was indeed supposed to pass outside the settlements — along the railway, near the Clover Bridge, along the Bypass Road, and through the forest belt of the village of Usatovo. But it turned out that all these land plots had already been sold, and it was practically impossible to pass there.
— In essence, the state program to connect the “Adzhalik” substation with the “Usatovo” substation was on the verge of failure, — Petr Moiseev believes. — We started thinking about how to resolve the situation. At the same time, the technical condition of the power transmission lines that already run from the “Usatovo” substation, both from the Adzhalik side and from the “MoldGRES” and “Novo-Odesskaya” lines, was assessed. Therefore, the issue of either passing along a new route or reconstructing one of the existing lines was considered. Since the technical condition of the “MoldGRES — Usatovo” line was worse than the “Novo-Odesskaya” line, it was decided to combine two tasks: to improve the operational characteristics of the “MoldGRES — Usatovo” line and to run the “Adzhalik — Usatovo” line along the same route. And, according to specialists, the voltage class does not change from this. After that, we ordered a correction of the project for the section of the “MoldGRES — Usatovo” line from Dachnoye to the entrance to the “Usatovo” substation. Our project passed the Ukrstroiinvestexpertiza and received a positive conclusion. At the same time, understanding that we somehow need to take into account the opinion of local residents of the two settlements, we approached the Usatovo and Nerubayka village councils to hear their proposals for changing the route within the villages. In Usatovo, relative to Sadovaya Street, it was shifted by 18 meters; in Nerubayka, the changes were not accepted.
Petr Moiseev’s phrase, “that we somehow need to take into account the opinion of local residents,” threw many of those present in the local House of Culture into disarray. Whose interests is “Ukrenergo” concerned about if the power line wires will hang over their homes? Why couldn’t they run the new power line through fields and forest belts, couldn’t they negotiate with the owners of those land plots and pay them compensation? Under Soviet rule, when people’s health was not a priority, they laid power lines, and now in independent Ukraine, people are again last. Now not only children but also grandchildren and great-grandchildren will have to live under a high-voltage line and acquire all sorts of ailments, people expressed indignantly.
They were not reassured by the assurances of other speakers: they said that with the commissioning of the new “Adzhalik — Usatovo” line, the reliability of the existing line would increase and the influence of the electric field would decrease. A storm of emotions was caused by the news that the EBRD had commissioned an independent expert examination by the Polish scientist Marek Zube, who gave a positive conclusion on the project. After all, the meeting did not explain one of the main conclusions of the expert from Poland, who writes in his report: “Currently, several residential buildings are located within the sanitary protection zone of the proposed line. Near most of these houses, the intensity of the electric field exceeds the permissible level of 1 kV/m, stipulated by Ukrainian norms, as well as the rules of some EU countries. According to Ukrainian norms, human habitation in these houses is not permitted.”
— My house is located only 9 meters from the high-voltage line, — says Zinaida Makovskaya, a resident of Nerubayka. — When the old pole in the garden was replaced with a new one, they destroyed the entire garden. They say they will compensate for the damage for each tree, each bush. But the working commission for compensation determined simply ridiculous prices. And it’s not about money, they won’t compensate us for the loss of health. Today, they only talk about the fact that we will receive compensation for housing, according to the resettlement action plan, which should be developed in the first quarter of this year. But I want to live in the house where my grandmother lived. My daughter was born in it, and she already has thyroid problems and neurosis. And this is a direct consequence of the increased electric field. By the time the resettlement plan is developed, and by the time it starts to be implemented, it will likely take more than one year. And we will live as if on a powder keg, so today’s sweet promises of energy company representatives do not reassure us at all.
— Today’s meeting with energy company representatives is a waste of time, — exclaims Svetlana Khodanovich, a deputy of the Nerubayka village council. — People still haven’t received answers to their specific questions, so they left the hall without listening to the speakers. They assured us that there were agreements with the two village councils. I have been a deputy since 2006, and I know that we have not made any decisions regarding permits for any work or land allocation. And this meeting was held to report to the EBRD.
A similar meeting took place with the residents of Usatovo a few days earlier, said Yuri Makoveychuk, chairman of the Usatovo village council. People also left the meeting indignant. All protest actions, appeals to the court, and to the Cabinet of Ministers have yielded no results.
Recently, a response came from the Ministry of Fuel and Energy, which leaves no hope for moving the power line beyond the village. In fact, the “Adzhalik — Usatovo” power line has practically already been built. No one thought about the people, their health, when they made adjustments to the original plan. Now people will have to live under the high-voltage line for decades. 76 houses, hundreds of residents, hostages of the power line, have fallen into the sanitary protection zone.