EBRD’s reaction to events in Usatovo has become known. A press release posted on the European Bank’s website states that the EBRD is “deeply concerned about the unauthorized change in the construction route of a high-voltage power line section in the Odesa region.” The original project, agreed upon with the bank, involved laying the power line outside the village, which was a condition for the EBRD’s participation in financing the project. The bank is equally concerned about the conflict situation and instances of physical confrontation between law enforcement agencies and residents of Usatovo village.
From the information posted on the EBRD website, it is known that the bank sent a written appeal to NEC “Ukrenergo,” demanding to immediately suspend construction work, “take measures to de-escalate tensions in the area, and cease proceedings in civil and criminal cases initiated against residents.”
In order to develop solutions acceptable to all parties, the bank offered NEC “Ukrenergo” its experience in resolving project-related conflicts.
The EBRD notified the company that the provision of financing for this project may be suspended until the bank assesses the environmental and social consequences of NEC’s decision to change the original route of the power line. Also, until NEC takes all necessary measures to properly resolve all environmental and social issues related to this change.
As we reported, the EBRD loan of 25.8 million euros, provided to NEC “Ukrenergo” for the modernization of trunk power grids, was approved in 2005 on the condition that the route of the new line would not pass through Usatovo.
The European Bank for Reconstruction and Development, it seems, does not forgive insubordination. The bank is owned by 61 countries. The bank’s goal is to promote the transition from centralized planning to a market economy in countries from Central Europe to Central Asia. Such a solid international structure, valuing its reputation, will not allow the “rules of the game” to be changed mid-way.
What, in that case, did the project implementers hope for? That local residents would not understand the situation or would remain silent? It didn’t work out. What’s left? A real threat to the project.
In its letter to NEC “Ukrenergo,” the EBRD emphasizes “the need to comply with the bank’s environmental and social policies, according to which its clients must adhere to internationally recognized standards for public disclosure, public consultation, and grievance redress.”
Earlier, we learned that the protracted conflict with the energy company forced the residents of Usatovo to seek help and support. The National Ecological Center responded with an appeal to the EBRD. The editorial office has the text of a letter from the coordinator of the National Ecological Center, Yuriy Urbansky, to the President of the EBRD, Thomas Mirow.
It contains a request for urgent measures regarding the conflict situation surrounding the EBRD-financed project for the reconstruction of the high-voltage network in the Odesa region – the “Adzhalik – Usatovo” power line.
The letter proposes, in particular, to suspend further negotiations between the European Bank and “Ukrenergo” regarding future projects until the incident in Usatovo is resolved in favor of the local residents. “Ukrenergo” is trying to obtain another loan from the EBRD – 170 million euros – for another power line construction project.
On Monday, when this issue of the newspaper was being prepared, a report appeared on the website “Timer-Odesa”: despite the demand of the European Bank for Reconstruction and Development, work on the installation of a high-voltage power line resumed in the village of Usatovo, Odesa region, which led to clashes between law enforcement officers and local residents.
Employees of the “Ukrenergo” company attempted to install one of the two remaining pylons on 2nd Vodoopiyanova Street but encountered active resistance from Usatovo residents. Then the energy workers moved to 3rd Vodoopiyanova Street. Ministry of Internal Affairs employees pushed back the protesters, which allowed work to begin. Several gardens and a greenhouse were destroyed in the process. There is no information about casualties. A “Timer” correspondent notes that threats against journalists were heard from the police.
A little later, a new message arrived: the National Energy Company “Ukrenergo” has suspended the construction of the “Adzhalik – Usatovo” high-voltage power line (HL) in the Belyaevsky district of the Odesa region. Nevertheless, the situation in Usatovo remains tense.